Tuesday, January 18, 2011

Well we had the meeting ANNNNDD......

There was nothing we could do re the size of the laundry so that is just UNFORTUNATE !

Darren was very sympathetic to the situation and told the carpenter to put extra noggins in the wall so that we can mount some sort of drying racks above the benchtop will see what we come up with ...
The power points and the antenna points will be fixed and we will attempt to have an extra power point put in the Garage.
The Cavity between rooms was at the wrong height and will be fixed.
The plasterers will be there later this week or early next week which is very exciting and Darren said that it will not be long now till LockUP soooo exciting ...
One step closer to completion.

Will keep you all posted of the developments in the next few days